Construction Log
(Last updated: 12/1/2006)
|
|
à Click on the “Day” number
for more detail ß |
|
Estimated
to take 4-1/2 months (134 days), highlights are presented chronologically |
|
Day |
Highlight |
A detail
or two left, but I say “we’re done” |
|
Hardwoods
sanded & finished |
|
Yard
graded & seeded |
|
Big Tub
whooshes to life; Closet shelving installed |
|
Finished
concrete, steps, and tile |
|
Overwhelmed
with conscientious tradesmen |
|
Gutters
installed, main house exterior prepped for paint |
|
Ceramic
tile, electrical service connected |
|
Final
paint and unfinished hardwood floor installation |
|
Prepping
for paint |
|
Sheetrock
hung |
|
New
window in, sheetrock delivered, mW RIP |
|
Brick
looks great, 4th Change Order |
|
Plumbing
woes |
|
Big Tub has
arrived |
|
Brick
delivered, exterior primed, HVAC roughed-in |
|
Roof
shingled, Big Door installed |
|
Wiring’s
in, crawlspaces connected |
|
|
|
Windows
are in |
|
Framers
kick butt |
|
3rd
Change Order, sleeping tour of the house |
|
Termites
in the old roof? |
|
Chimney
work & framing starts; 2nd Change Order |
|
Blocks
laid |
|
Footings
poured |
|
Footings,
Boo boos, & 1st Change Order |
|
Site prep
– Tree removal |
|
Site prep
– Patio removal |
|
February
28, 2006: “Before” pictures |