Re: Mussels and Wilson dam lock


[ Follow Ups ] [ Post Followup ] [ North Alabama Fishing Forum ] [ FAQ ]

Posted by Kerry Grissett on August 20, 2006 at 20:31:25:

In Reply to: Mussels and Wilson dam lock posted by Danny Blackburn on August 20, 2006 at 20:11:48:

Haven't heard anything about the mussels lately.

Here's what WAFF TV (UHF-48) Huntsville has on their web site (Dated 8/17/2006):

*****

Gate removed from damaged lock at
Wilson Dam

A miles-long backup of barges on
the Tennessee River should begin
clearing, soon now that a damaged gate has been removed
from a lock at Wilson Dam.

The main lock at the dam has been closed since Aug. 3,
after a barge became entangled in the lift gate and
lifted it off its tracks.

An auxiliary lock was opened after the accident, but it's
smaller and operates much slower than the main lock.

The main lock can lift or lower a cluster of nine barges
in about 45 minutes.

The auxiliary lock requires about 75 minutes to move a
single barge.

With the damaged gate now out of the way, engineers plan
to use a temporary gate on the main lock to clear miles
of backed-up barges above and below the dam.

Full repairs are expected to take eight weeks.

*****

Good luck and good fishin'


Follow Ups:



Post a Followup

Name:
E-Mail:

Subject:

Comments:

Optional Link URL:
Link Title:
Optional Image URL:


[ Follow Ups ] [ Post Followup ] [ North Alabama Fishing Forum ] [ FAQ ]